Water > Hargrave St Pump Station

Client

City of Port Adelaide/Enfield Council

Scope

Containerised Switchroom, Generator Switchboard & amp; Main Switchboard

Value

$300,000+

Time Frame

9 Months

Delivered

VIP Electrical

Comments

In 2014 Lai Switchboards was Engaged by VIP Electrical to complete the complete Switchroom / Switchboard solution for the Hargrave Street Pump Station in Adelaide.
The work performed by Lai Switchboard included the following

•Containerised Switchroom c/w General L&P, Stairs, Supports & Inner Dividing Wall.
•250A Form 3B Main Switchboard Installed into Switchroom.
•800A Form 3B Generator Switchboard Installed into Switchroom.
•All Interconnecting Cabling Between Main Switchboard & Generator Switchboard  before Delivery to Site.

Short lead times & high Quality standards were key for this particular project & Lai Switchboards delivered the whole project successfully & at a very high Standard.