Utility Infrastructure > Mount Majura PV Solar Farm

Client

UGL Limited

Scope

Lai Switchboard were engaged by UGL Limited to design and manufacture the required switchboards and deliver them within a 12 week time line.

The switchboards supplied for this project included:

-          2x 2000A Grid Connection Cubicles

-          22x Sub Array Switchboards

Value

250 K

Time Frame

16 Weeks

Delivered

12 Weeks

Comments

Mount Majura Solar farm is a 2.3MW solar farm located 15km north-east of Canberra.
Lai Switchboards worked closely with UGL Limited to design and manufacture the switchboards to meet the requirements of the relevant standards while also meeting the client’s requirements for size limitations and a fast delivery.
The Lai Switchboards team were able to manufacture the 22x Sub Array Switchboards in less than 2 weeks from receiving approval to manufacture.