Commercial > Adelaide Oval Redevelopment

Client

AOSMA

Scope

LV Main Switchboards and Distribution Boards

Value

$1.7 Million

Time Frame

18 Months

Delivered

Lend Lease

Comments

LAI Switchboards were successful in supplying the switchboards for the Western Grandstand upgrade in 2009. So in 2011 when they decided to upgrade the entire oval, the $535 Million Adelaide Oval Redevelopment project saw the need to source a switchboard manufacturer with the capabilities of producing a quality product while keeping up with the timeframe of the project.

Switchboard designed and manufactured by LAI Switchboards consisted of :
- 4 x 4000 Amp Main Switchboards
- 4 x Power Factor Correction Switchboards
- 34 x Main Distribution Boards
- 34 x Essential Main Distribution Boards
- 120 x Distribution Boards

Space for C-Bus control was included in each distribution board, with the Electrical contractor pre-programming the C-Bus modules for LAI Switchboards to fit during the manufacturing phase, this ensured a fast on-site installation and commissioning period.
 
Along with the main oval redevelopment LAI Switchboards were also engaged to retro-fit the lighting tower switchboards to include C-Bus control, with the tight space inside the lighting tower and the requirement to have equipment changed over between cricket night games was a challenge however successfully executed by LAI Switchboards.