Oil & Gas > Charlie Field Compressor Station Instrument Room

Client

ABB Australia / QGC

Scope

D/C Design and Manufacture 26m x 5.5m switchroom.
Mechanically Install 53 x Control Panels.
Cable Ladder and conduit install.
Completion of Electrical internal interconnection wiring.

Value

800 K

Time Frame

12 Months

Delivered

11 Months

Comments

QGC, Shell and ABB UK designed the system. Worley and QGC had a strong emphasis on Quality Management and documentation. Lai worked closely with ABB at all stages to ensure documentation was put through the rigorous approval process. Fabrication of structural room components was conducted in Adelaide. Worley and QCG required regular inspections all stages of room assembly. For this reason the assembly, final fitout and wiring was completed in Brisbane. Lai Switchboards met the challenge of managing many stakeholders and manufacturing locations to bring together 1 final solution.