big project experience
The easy way to do business is the Lai way
delivering on time, on budget australia wide
Passion, experience and understanding - the Lai promise
Corporate Video

Commercial > Mile End Data Centre

Client

Adam Internet

Scope

Stage 1 : 1x 3200 Amp 50kA Main Switchboard. 2x 2000 Amp 50kA UPS Switchboards. 1x 3000 Amp 25kA Generator Switchboard.

Stage 2 : 4x 168 Way Distribution Boards with power monitoring for each circuit. 2x 84 Way Distribution Boards with power monitoring for each circuit. 1x 250 Amp General Light & Power Distribution Board. 1x 400 Amp Tenancy Distribution Board.

Value

$6m + (Stage 1)

Time Frame

8 months (stage 1)

Delivered

Frostec Group

Comments

Adam Internet undertook a $6 million investment project to build the Adam Data Centre. From concept to completion this project has spanned only 8 months of 2009 meaning some fast work to get the 350 rack capacity centre ready for business.
 
Following the success of Stage 1, In 2012 Adam Internet undertook stage 2, another multi-million dollar project adding a further 150 rack capacity.
 
Lai Industries worked closely with Frostec Group with the design and construct brief